Auditing the Implementation of EC Plan and Target

Pursuant to Section 11 (8) and Section 22 of the ECP Act 1992 (B.E. 2535) in combination with the Ministerial Regulation that requires the owner of designated factory / building to audit the implementation of EC plan and target by reporting an audit result in part 4 of the Form Bor Por Ror 1 for submitting an energy production, consumption and conservation for designated factory or in part 3 of the Form Bor Por Or 1 for submitting a building usage, energy consumption and conservation for designated building.        

        Guidance on Energy Conservation by the ECP Act 1992 (B.E.2535) for the Designated Factory and Building      

        Ministerial Regulation   Re:  Criteria, Methods and Timeline for Determining the EC Plan and Target and Auditing the Implementation of  EC Plan and Target for Designated Factory and Designated Building 2004 (B.E.2547)

        Guidance on Establishing the EC Plan and Target for Designated Factory  

        Guidance on Establishing the EC Plan and Target for Designated Building

        Ministerial Regulation    Re:  Criteria, Methods and Timeline for Recording and Submitting the  Energy Conservation Data 2004 (B.E.2547)

        Instruction on Filling-in the Form : Bor Por Ror 1 and Bor Por Ror 2 by Designated Factory  

        Instruction on Filling-in the Form : Bor Por Or 1 and Bor Por Or 2 by Designated Building  

Punishment for Violators

      1.  The owner of designated factory / building does not audit the implementation of  EC plan and target and submit to DEDE, shall be fined at not over 100,000 baht  (Section 56).

       2.  The owner of designated factory / building or the PRE who does endorse the facts for auditing the implementation of EC plan and target as faults, shall be imprisoned for not exceeding 1 month or shall be fined at not over 50,000  baht , or both (Section 57)